Construction of unit 4 of China's Tianwan听nuclear power plant听has entered a new phase with the installation of its containment dome.听
![]() |
| Tianwan 4's dome is craned into place (Image: CNNC) |
Installation of the dome was completed ahead of schedule on 26 September听and marks the end of the civil construction phase at the project, China National Nuclear Corporation (CNNC) said. The project now enters the equipment installation phase.
The operation to lift the dome into place took less than two hours, using a similar lifting program used听at Tianwan 3. Innovations to the lifting process have resulted in overall time savings of nearly听two months compared with the similar construction stage at Tianwan units 1 and 2, CNNC said.
Tianwan 4 is the second of two AES-91 VVER-1000 units designed by Gidropress, a subsidiary of Russian state nuclear corporation Rosatom.听Two similar units that have been in commercial operation at the in Jiangsu site since 2007. AtomStroyExport, another Rosatom subsidiary, is the main contractor, supplying the nuclear island. Construction work began on unit 3 in December 2012, with unit 4 following in September 2013. The units are expected to start operation in 2016 and 2017 respectively.
Researched and written
by 抖阴传媒在线 Nuclear News