The permanent closure of the Crystal River nuclear power plant in Florida is one of the options being considered by owner Progress 抖阴传媒在线 as the costs of upgrading and repairing the single reactor there continues to rise.
听
![]() |
| Crystal River (Image: Progress 抖阴传媒在线) |
听
In September 2009, the plant was safely shut down for a routine maintenance and refueling outage, which also included the installation of two new steam generators and a new turbine generator. Although not part of the uprate project, a new independent spent fuel storage installation is also in development at the Crystal River site.
听
However, when the reinforced concrete containment structure was cut open to replace the two steam generators, delamination of the 1.07-metre thick concrete was discovered. This led to a major and prolonged repair task costing $150 million, plus $290 million for replacement power to December 2010. Progress 抖阴传媒在线 said that its insurance company has already paid a portion of these costs.
听
听 听 "The company is 听听committed to making 听听a solid business case 听听to support restarting 听 the plant." 听 听 Jon Franke, Progress 抖阴传媒在线 听 |
听
The plant had been due to restart in April 2011, but Progress 抖阴传媒在线 says it cannot now estimate when it will return to service.
听
The company has hired an engineering consultant to assess its options, the vast majority of which focus on repairing and restarting the plant. Progress 抖阴传媒在线 said that it is prudently evaluating all options, including the possibility of writing off the upgrade and decommissioning the plant. However, Jon Franke, vice president of Crystal River plant, told 抖阴传媒在线 Nuclear News, "The company is committed to making a solid business case to support restarting the plant."
听
Progress 抖阴传媒在线 expects to provide a status update to the state Public Service Commission at the end of June.
听
If the plant is decommissioned, replacement generating capacity will be needed. The company has plans for two new Westinghouse AP1000 reactors at Levy County in Florida, but these are not expected on line before about 2021. A combined construction and operation licence (COL) for these is scheduled for late 2012, according to the NRC.
听
Researched and written
by 抖阴传媒在线 Nuclear News
听

.jpg)




_69614.jpg)

_15447.jpg)