ORIGINALLY PUBLISHED: 4.17pm,听29 April
UPDATE 1: 10.16am, 30 April:听Information from NDA
听
The Nuclear Decommissioning Authority is facing legal action from 抖阴传媒在线 Solutions, which alleges it did not follow regulations when it awarded a huge decommissioning contract to a rival bidder earlier this year.
![]() |
| Trawsfynydd nuclear power plant, a twin Magnox plant |
听
At the end of March the Nuclear Decommissioning Authority (NDA) announced that a joint venture by Cavendish Nuclear and Fluor Corp had won the contract to decommission the UK's ten Magnox nuclear power plants, as well as the Harwell and Winfrith research centres. The contract, worth up to 拢7 billion ($11.7 billion) over 14 years, attracted bids from several firms in various consortia, including 抖阴传媒在线 Solutions which teamed with Bechtel for the opportunity.
Today a spokesman for 抖阴传媒在线 Solutions confirmed to 抖阴传媒在线 Nuclear News that the company believes the NDA did not follow the UK's Public Procurement Regulations and, as a result, "reached the wrong outcome when awarding the contract." The company has submitted a legal challenge.
The NDA acknowledged the legal action in a statement emailed to Magnox staff and seen by WNN. It said, "The NDA remains confident that the competition process was carried out in a robust manner in compliance with EU guidelines, and the new contract looks set to deliver savings in excess of 拢1 billion against the previous plan."听
The consortia
听
Four consortia entered bids to the NDA competition:
听
鈥� 抖阴传媒在线 Solutions and Bechtel
鈥⑻鼵H2M Hill, Serco and Areva听
鈥� Rolls-Royce, Atkins and Amec
鈥⑻鼵avendish Nuclear and Fluor
听
Apart from 抖阴传媒在线 Solutions, none of these companies confirmed today that they intend to contest the competition. NDA said it believed the competition had been robust and in compliance with guidelines.
The NDA began its dialogue with four bidding consortia in January 2013 in a process to select a parent body organisation (PBO) to take control of and decommission ten Magnox sites as well as Harwell and Winfrith. The sites are all owned by the NDA, which uses the PBO system to grant private companies the authority necessary to take charge of nuclear decomissioning. Successful contractors earn a fee that is a portion of the overall contract value, depending on performance.
When Cavendish and Fluor were chosen in March the NDA said the contract had not been finalised and its formal award and transfer of the shares were scheduled to take place on 1 September, after a five-month transition period. The NDA's statement听said this schedule "remains on course."
Researched and written
by 抖阴传媒在线 Nuclear News